KEY POINTS

  • IONITY Elverum, Norway: Ekoenergetyka 500 kW pilot, opened Dec 2025

  • 6 incident reports, pyrofuses fired, chargers to be replaced

  • Now Huawei: 720 kW power unit, 3 dispensers, 6 charge points

  • Deal announced at the Huawei stand, Power2Drive, June 2026

  • Huawei already runs at 5 Electra sites I know of

AI illustration, not a real photo: a white Huawei-style fast charging dispenser in IONITY branding with a magenta 600 kW MAX label, a touchscreen, two liquid-cooled cables and the IONITY logo running vertically.

AI illustration of a Huawei dispenser (previous generation) in IONITY design

Where this started

Two weeks ago I wrote about IONITY Elverum (Østerdalsporten) in Norway. It was the only IONITY site listed at 500 kW: Ekoenergetyka's split solution with AXON SAT 400 (dispenser) and AXON SIDE DLBS (power unit), opened in December 2025. IONITY called it their first pilot of this technology.

Then came six incident reports. The cars' pyrofuses fired while charging. IONITY told Adressa that the charger manufacturer had confirmed a fault and that the chargers would be replaced. When I looked, the whole site was offline.

A pilot is there to prove something. Unfortunately, this was not a successful pilot.

Yesterday it was back online

Yesterday I saw Elverum online again. This time, instead of 6 charge points at 500 kW, 4 were at 600 kW and 2 at 500 kW. So I talked to my network and found the surprising, or let's say, my expected replacement.

Huawei. Yes! Huawei at IONITY.

  • 1 power unit, 720 kW

  • 3 dispensers

  • 6 charge points

The two 400 kW points on site are Alpitronic. They are not part of this.

I think it was easy to install. The cable works already existed, because the Ekoenergetyka setup was also a split system: power cabinets in one place, dispensers at the parking bays.

Huawei charging display from 2025: an open liquid-cooled power unit on the left, a red dispenser and a gray dispenser in the middle, and a screen labeled Successful Cases on the right.

Huawei power unit and dispensers, 2025

I have been keeping these photos for four months

Large screen at the Huawei stand at Power2Drive showing the Huawei and IONITY logos side by side with the line Jointly Forging the New Gold Standard of EV Charging, dated June 23rd, 2026, Munich, Germany.

Huawei and IONITY, Power2Drive, 23 June 2026

At Power2Drive in Munich in June, IONITY and Huawei announced the deal at the Huawei stand. It lasted maybe five minutes. I was there, took these photos and kept them. I was waiting to see it in reality before I posted them.

Two white Huawei fast charging dispensers on display at Power2Drive 2026, one labeled 600A and one labeled 800A, each with a liquid-cooled CCS cable.

Huawei 600 A and 800 A dispensers, Power2Drive 2026

Here it is.

AI illustration, not a real photo: the same IONITY Elverum site in winter with three white Huawei-style dispensers in IONITY branding and a single power unit cabinet on the left.

After: AI illustration of Huawei at IONITY Elverum

Now Huawei has to prove it

This is now Huawei's pilot, at one of Europe's biggest charging networks. And they have to prove it.

Huawei is not new to European CPOs. I know of 5 Electra sites already running Huawei (France, Germany, Italy and the Netherlands). And we all know Electra is one of the fastest-scaling CPOs, while keeping a really good reputation for site design and reliability.

Earlier this week I explained that they even took over 374 charge points from Mercedes-Benz Charging. Check it here: Newsletter | Video

This is the make or break moment. If it works out at IONITY, it is on the scale of EnBW working with XCharge.

I wrote about that one in detail in February and made the claim that XCharge would become EnBW's second supplier. The first reaction was strong denial. Even former XCharge employees were amused and did not believe it. When it happened, I was congratulated by the brains at EnBW. 😄

So today I am telling you: Huawei is there. Now let's see.

Investing in charging sites? Work with me.

Work with me. Three ways I can help, one free call to start. Site owners and CPOs: right hardware and specs, lower TCO and right prices, execution with planning, installation and maintenance. Charger manufacturers: GTM strategy, competition overview, building channel and service partners. Have a site to electrify in Germany, the Netherlands or Belgium? Whether AC or DC, I can help, reach out. All three start with a free 20-minute call: email haseeb@etechvolution.com. 400+ DC chargers sold, 600+ in my database, 130,000+ DC points.

About Me:

I am an independent e-mobility consultant. I worked at a charger manufacturer and sold 400+ DC fast chargers in Germany before going on my own. I have built a database of 600+ DC chargers available in the EU, with their strengths and weaknesses. I have a network of EPCs, turnkey solution providers and service partners, so I hear about market shifts in real time. And I have mapped 130,000+ DC charging points across Europe, down to the charger maker behind each charge point. So I see which chargers are being installed, and which are being replaced.

Email me at [email protected]. Let's discuss your project!

Sources

Reply

Avatar

or to participate